I have an old bathroom (Length 2.5m x Width 2.5m x Height 2.6m) that has been stripped back to bare walls, joists.
All existing plaster,ceiling, tiles, floor etc... have been removed.
The scope of works is
- Dot and Dab new drylining to all walls
- Install new 12.5mm plasterboard ceiling
- Skim plaster ceiling only
- Install new WB 18mm plywood floor with timber noggins every 500~600mm
- Tank floor/ walls with membrane
- Tile all 4No. walls
- Tile floor
- Install new bathroom suit inc of:
Back to wall WC with concealed cystern.
'Box out' cystern of plywood and tiled.
Hang cantilivered wall mounted vanity unit with mirror and wall unit.
Install new radius shower unit
- Plumb new bathroom suite as per above.
.
All materials by customer.
Customer to install shaver socket/ electrics and radiator/
towel rail units.
Existing waste water connections for basin and shower 'below floor' as per new units.